Dominion Energy and Duke Energy cancel Atlantic Coast Pipeline project, triggering $2.7B-$3.2B charges
DDominion Energy, Inc
On July 5, 2020, Dominion Energy and Duke Energy announced the cancellation of the proposed 600-mile natural gas pipeline due to permitting delays and legal challenges that increased costs from an original estimate of $4.5 billion to $8 billion. The decision was approved by Dominion's Board on July 2, following a Montana district court ruling overturning federal permit authority for waterbody crossings. Dominion Energy will recognize estimated pre-tax charges between $2.7 billion and $3.2 billion related to the project and associated Supply Header pipeline, with most reported in second quarter earnings.