Dominion Energy updated its Coastal Virginia Offshore Wind (CVOW) project, reporting that estimated total costs have…

DDominion Energy, Inc

Dominion Energy updated its Coastal Virginia Offshore Wind (CVOW) project, reporting that estimated total costs have increased from approximately $11.2 billion to $11.5 billion due to tariff-related expenses and a temporary work suspension. As a result of these factors, the project's expected completion date has been pushed to early 2027.