IntrinsicIntrinsic

Other Events · · Intrinsic team

NCUC delays Duke Energy Carolinas rate case hearing amid partial settlement on storm costs

DUK-PADuke Energy Corp

Duke Energy Carolinas reached a partial settlement with the Public Staff of the North Carolina Utilities Commission regarding deferred storm recovery costs from Hurricanes Florence and Michael. The agreement removes these $193 million costs from the general rate case, requiring DEC to file for securitization financing within 120 days of an NCUC order on their reasonableness. A recovery rider is established at zero initially. Separately, due to COVID-19 uncertainty, the NCUC suspended the procedural schedule in Duke Energy Progress's rate case, delaying hearings originally set for May 4.

More from Duke Energy Corp

Explore DUK-PA