Hydro One Networks Inc. filed a joint leave-to-construct application with the Ontario Energy Board on September 11…

HRNNFHydro One Ltd

Hydro One Networks Inc. filed a joint leave-to-construct application with the Ontario Energy Board on September 11, 2026, seeking approval for the $1.3 billion North Shore Link project. This new 230-kilovolt transmission line will connect Mississagi Transformer Station near Wharncliffe to HOSSM-owned Third Line TS in Sault Ste. Marie, with service expected by 2029. The investment aims to strengthen grid resiliency and support economic growth in Ontario's northeast, incorporating a First Nation Equity Partnership Model for potential minority ownership. Hydro One Limited operates as Ontario’s largest electricity transmission and distribution provider.