Other Events ·
On September 10, 2026, Ionic Digital Inc. announced that the Electric Reliability Council of Texas (ERCOT)…
IONDIonic Digital Inc.
On September 10, 2026, Ionic Digital Inc. announced that the Electric Reliability Council of Texas (ERCOT) provisionally classified its remaining 466 megawatt energization request for the Ward County campus as Base Load in ERCOT’s Batch Zero process. This classification allows the company to proceed with energizing the final tranche, bringing the campus's total aggregate demand to 700 MW. The Company targets full energization by the end of 2027, though the status remains provisional pending ERCOT verification and oversight by the Public Utility Commission of Texas. Ionic Digital operates in the high-performance computing and data center infrastructure industry, providing ready-to-use assets for AI workloads.