ONEOK reached a settlement with insurers and reinsurers to resolve all physical damage and business interruption claims related to the July 2022 Medford NGL facility incident. The total insurance payment is $930 million, including $100 million already received; the remaining balance must be paid within 45 days. ONEOK plans to use these proceeds to build a new 125,000 barrels per day (bpd) NGL fractionator at its Mont Belvieu, Texas facility. This project is expected to cost approximately $550 million and take about 24 months to complete, increasing total fractionation capacity in Mont Belvieu to roughly 700,000 bpd. The new unit will produce purity ethane rather than the ethane/propane mix previously produced at Medford. ONEOK is a leading midstream service provider.