Oneok Inc: Restarts construction of Demicks Lake III and MB-5 projects for $390M total
OKEOneok Inc
ONEOK announced plans to restart construction on two previously announced infrastructure projects: the 200 MMcf/d Demicks Lake III natural gas processing facility in North Dakota, expected to cost approximately $140 million with completion targeted for Q1 2023; and the 125,000 bpd MB-5 NGL fractionator in Mont Belvieu, Texas, expected to cost approximately $250 million with completion targeted for Q3 2023. The company stated that increasing producer activity and improving demand drove the decision to restart these projects, noting that remaining capital investment is significantly less than building greenfield facilities.