PG&E Corp: CPUC judges propose $13.82B revenue requirement for 2023, below requested amount

PCGPG&E Corp

The California Public Utilities Commission issued a proposed decision and an alternate proposed decision in PG&E's 2023 general rate case Phase 1 Tracks 1 and 2 proceedings. The PD would authorize $13.82 billion revenue requirement for 2023, while the APD proposes $13.31 billion; both are lower than the requested amount of $15.41 billion. For subsequent years, the PD authorizes $14.47B (2024), $14.73B (2025), and $14.85B (2026). The APD proposes lower amounts for each year. Key differences involve undergrounding miles: PD supports 200 miles, while the Utility requested 2,000 miles; APD supports 973 miles. Track 2 settlement approves $221 million cost recovery over 2023-2024.