Georgia Power announced a schedule update for Plant Vogtle Units 3 and 4, projecting in-service dates of the third quarter 2022 for Unit 3 and the second quarter 2023 for Unit 4. The delay for Unit 3 is driven by additional remediation work, construction productivity issues with electrical installations, and slower system turnovers. For Unit 4, delays stem from resource diversion to support Unit 3 efforts. Georgia Power expects further details on capital cost forecasts in its Q3 2021 Form 10-Q.