Invests $400M-$625M in four new flat roll steel coating lines across Southern and Midwest U.S
STLDSteel Dynamics Inc
Steel Dynamics announced plans to invest between $400 million and $625 million in four new value-added flat roll steel coating lines. Two lines, costing approximately $225 million, will be located in the Southern U.S. near its Sinton Texas EAF mill; these include a 300,000-ton galvanizing line with Galvalume capability and a 240,000-ton paint line. The company expects production to begin in the second half of 2022. Additionally, Steel Dynamics plans to invest between $175 million and $200 million for two similar coating lines (300,000-ton galvanizing with Galvalume capability and a 240,000-ton paint line) in the Midwest U.S., also expected to start production in late 2022. These initiatives aim to diversify product offerings, increase cash generation, and reduce reliance on foreign imports for coated steel products.