Consolidated Water awarded $39.8M design-build contract for Pismo Beach water facility

CWCOConsolidated Water Co. Ltd.

PERC Water, a U.S. subsidiary of Consolidated Water Co. Ltd., entered into a fixed-price design-build agreement with the City of Pismo Beach, California, valued at approximately $39.8 million. The project involves designing and constructing the Central Coast Blue Advanced Water Purification Facility to produce 500 acre-feet of purified water annually in its initial phase, with provisions for future expansion to 750 acre-feet. Substantial completion is targeted by September 17, 2028, subject to a 703-day schedule from the October 15, 2026 kick-off date. The company develops and operates advanced water treatment plants and distribution systems globally.

More from Consolidated Water Co. Ltd.

Explore CWCO