Duke Energy Corp: Settlement cuts coal ash cleanup costs by $1.5B to total $8-9B

DUKBDuke Energy Corp

Duke Energy Carolinas and Duke Energy Progress entered a settlement with the North Carolina Department of Environmental Quality and Southern Environmental Law Center on December 31, 2019. The agreement requires excavation of seven of nine remaining coal ash basins in North Carolina, moving ash to lined landfills at Allen Steam Station, Belews Creek, Mayo Plant, Roxboro Plant, Rogers Energy Complex, Marshall Steam Station, and Roxboro Plant. Litigation related to the April 2019 DEQ closure order is dismissed. The settlement reduces estimated undiscounted costs for closing these basins by approximately $1.5 billion compared to prior estimates of $4-5 billion. Total estimated cost for all ash basin closures in North Carolina and South Carolina now stands at $8-9 billion, with $2.4 billion spent through 2019. Remaining spend is expected over the next 15-20 years.