Other Events · · Intrinsic team
Southern Co: Georgia Power projects Plant Vogtle Unit 4 in-service date slips to Q2 2024 after remediation of cooling system vibrations
SOSouthern Co
Southern Nuclear identified and remediated vibrations associated with certain piping within the cooling system during start-up and pre-operational testing for Plant Vogtle Unit 4. Georgia Power now projects that the unit will enter service during the second quarter 2024, a schedule extension from previous expectations. The delay is not expected to affect total project capital costs; however, any further extension beyond Q2 2024 could result in additional base capital costs of up to $15 million per month charged to income. Additionally, if commercial operation for Unit 4 does not begin by March 31, 2024, Georgia Power's return on equity used for Nuclear Construction Cost Recovery tariffs will be reduced to zero, resulting in estimated negative earnings impacts of approximately $30 million per month until the following month.