Other Events · · Intrinsic team
Southern Co: Georgia PSC approves $7.56B recovery for Plant Vogtle Units 3 and 4 costs
SOSouthern Co
The Georgia Public Service Commission approved a stipulated agreement allowing Georgia Power to recover $7.562 billion in construction and capital costs plus $1.02 billion in associated retail rate base items for Plant Vogtle Units 3 and 4, exceeding the previously certified amount of $4.418 billion. The approval resolves issues regarding cost reasonableness and prudence. Georgia Power will record a pre-tax income credit of approximately $228 million ($170 million after tax) in Q4 2023 for costs now recoverable through retail rates. Annual retail base revenues are expected to increase by approximately $729 million, with average retail base rates adjusted by about 5% effective the first day of the month following Unit 4's commercial operation.