Southern Co: Georgia PSC staff and Georgia Power reach stipulated agreement on $7.56B Vogtle cost recovery
SOSouthern Co
On August 30, 2023, the Georgia Public Service Commission (PSC) Public Interest Advocacy Staff filed a stipulated agreement with Georgia Power to resolve issues regarding the reasonableness and prudence of costs for Plant Vogtle Units 3 and 4. If approved by the PSC, Georgia Power will recover $7.562 billion in total construction and capital costs plus $1.02 billion in associated retail rate base items. Upon Unit 4 achieving commercial operation, annual retail base revenues would increase approximately $729 million and average rates adjust by about 5%. The agreement requires a vote to continue construction if adverse events occur; Georgia Power voted to proceed. A dispute with co-owners regarding cost-sharing remains unresolved, potentially leading to pre-tax charges of up to $345 million.